doesnt metter, even you save it in version 2003 (MSP), IT Atually uses the software system currently installed on your machine (in this case its MSP 2007).
you have to have MSP 2000, 2002/3 in order to import a MS project files into Primavera 5 or 6
but i am still looking for solutions.
cheers
Member for
19 years 10 months
Member for19 years10 months
Submitted by Cherie S Blare on Fri, 2008-06-06 06:32
Why not save in MSP 2003 ( as you can in MSP 2007 ) and then import / open up in P6 ? I think this can only be done in standalone P6 - not intranet licence based.
Regards
Cherie
Member for
19 years 9 months
Member for19 years9 months
Submitted by Shahzad Sikandar on Tue, 2008-06-03 12:10
Member for
19 years 10 monthsRE: Import form MSP 2007 to Primavera 6.1
Ok. Good Luck.
Member for
19 years 9 monthsRE: Import form MSP 2007 to Primavera 6.1
Cherie
doesnt metter, even you save it in version 2003 (MSP), IT Atually uses the software system currently installed on your machine (in this case its MSP 2007).
you have to have MSP 2000, 2002/3 in order to import a MS project files into Primavera 5 or 6
but i am still looking for solutions.
cheers
Member for
19 years 10 monthsRE: Import form MSP 2007 to Primavera 6.1
Why not save in MSP 2003 ( as you can in MSP 2007 ) and then import / open up in P6 ? I think this can only be done in standalone P6 - not intranet licence based.
Regards
Cherie
Member for
19 years 9 monthsRE: Import form MSP 2007 to Primavera 6.1
ok
thanks very much
Member for
24 years 6 monthsRE: Import form MSP 2007 to Primavera 6.1
The installation of MSP 2007 disables the import feature of P6.
Unloading MSP 2007 may resolve your problem.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au