1.Is the last task in your schedule a milestone? then MS Project does not display critical milestones in red and not-critical ones in blue as it does for norlmal tasks
Is the last task milestone a critical one?
2. Do you have recurring tasks in your schedule?
then check the Start No Earlier Than date of the last occurence, and the one before last, ... until you find that this occurence is starting later than the last task at the bottom of the schedule
Hope this help
Alexandre
Member for
19 years 11 months
Member for19 years11 months
Submitted by Trevor Rabey on Mon, 2008-04-28 11:39
Member for
17 years 9 monthsRE: Critical Path / Critical Activities
it worked!!
Thanks a lot for your valuable info
Alex
Member for
22 years 9 monthsRE: Critical Path / Critical Activities
Alex,
Project, Filter for, Critical Task
1.Is the last task in your schedule a milestone? then MS Project does not display critical milestones in red and not-critical ones in blue as it does for norlmal tasks
Is the last task milestone a critical one?
2. Do you have recurring tasks in your schedule?
then check the Start No Earlier Than date of the last occurence, and the one before last, ... until you find that this occurence is starting later than the last task at the bottom of the schedule
Hope this help
Alexandre
Member for
19 years 11 monthsRE: Critical Path / Critical Activities
Check the Schedule Table to see the ES, EF, LS, LF, free slack and total slack.
Run the Gantt Chart Wizard to format Critical Tasks red.
Check Tools, Options, calculation to see that Critical is defined as zero total slack.
Member for
18 years 3 monthsRE: Critical Path / Critical Activities
Tools | Options | Calculation-tab.
Put a check mark in the box "Calculate multiple critical paths"
View | Tracking Gantt
(I *so* miss NZ -- did the Milford, went as far north as 90 Mile Beach, would love to live in Napier.)