MSP Baslines

Member for

19 years 10 months

Andrew



Make sure the activities are logic linked correctly, that you have no constraints, you have a critical path identified wthin the project etc.



When updating a project you must save the baseline firstly ( Save Baseline ).



Go into Tracking Gantt.



Insert Columns .... Activity Name / Baseline start / baseline finish / Actual Start / Actual Finish Per complete



Go to Tools > Tracking > Progress Lines > Input the data / progress line date.



Input the ACTUAL Start and Finish Dates against each activity. If some activities have started but are incomplete then you must put in a percentage.



The project is now being progressed.


Member for

21 years 7 months

Hello Alexandre ,



Yes I am posting the progress in the tracking option.



Andrew

Member for

22 years 9 months

Andrew,

are you entering the progress in the tracking table fields?

Alexandre