To bring MS Project 2000 data directly into P3 perform the following:
1. From within P3, select Tools, Project Utilities, Export
2. Under the Content section, export the data that you would like to bring into P3 from MS Project.
Example: If you want to populate Activity ID, Original Duration, and Remaining Duration with data from MS Project, select Activity ID, Original Duration, and Remaining Duration as your export content.
3. Under the Format section, select WK1 or DBase as the file type to be created by Exporting.
4. From within MS Project 2000, save the project as an Excel Workbook.
5. Open the MS Project Excel Workbook, and the export file created by P3, in Excel.
6. Using copy and paste, populate the fields under each appropriate column in the P3 export file, with the data from the MS Project Excel Workbook.
7. Save the export file (be sure to keep it in WK1 or DBase format). You will now use it as the import file to bring the data into P3.
8. From within P3, select Tools, Project Utilities, Import.
9. When prompted, enter the path and file for the updated P3 export file, and click Run.
Bonne chance
JK
Member for
21 years 3 months
Member for21 years3 months
Submitted by sylvia peyron on Thu, 2008-01-31 13:51
I think even with the link it will still not help as the original post started by saying no access to MSP98. Hence the poster has no access to create the MPX in the first place never mind convert it thereafter.
You have to download converter file from primavera knowledge base to do the conversion of MSP 2000 file format directly into MPX file, then Click --> Tools --> MPX conversion utility, then select the MPX file to convert it into P3 files
Member for
18 years 1 monthRE: MSP2000 converion P3
Helo sylvia,
Try this it could help:
To bring MS Project 2000 data directly into P3 perform the following:
1. From within P3, select Tools, Project Utilities, Export
2. Under the Content section, export the data that you would like to bring into P3 from MS Project.
Example: If you want to populate Activity ID, Original Duration, and Remaining Duration with data from MS Project, select Activity ID, Original Duration, and Remaining Duration as your export content.
3. Under the Format section, select WK1 or DBase as the file type to be created by Exporting.
4. From within MS Project 2000, save the project as an Excel Workbook.
5. Open the MS Project Excel Workbook, and the export file created by P3, in Excel.
6. Using copy and paste, populate the fields under each appropriate column in the P3 export file, with the data from the MS Project Excel Workbook.
7. Save the export file (be sure to keep it in WK1 or DBase format). You will now use it as the import file to bring the data into P3.
8. From within P3, select Tools, Project Utilities, Import.
9. When prompted, enter the path and file for the updated P3 export file, and click Run.
Bonne chance
JK
Member for
21 years 3 monthsRE: MSP2000 converion P3
Hi,
Yes well spotted, and it is even worse because they upgraded to MSP2002...
Cheers
Sylvia
Member for
24 years 4 monthsRE: MSP2000 converion P3
I think even with the link it will still not help as the original post started by saying no access to MSP98. Hence the poster has no access to create the MPX in the first place never mind convert it thereafter.
Member for
18 years 5 monthsRE: MSP2000 converion P3
Here it goes, sylvia.
http://www.eh.com.au/Technical%20Papers/030804%20Converting%20to%20and%…
Hope this shud help you out.
Cheers,
Ravi
Member for
19 years 7 monthsRE: MSP2000 converion P3
send to me the file and ill try to do it for you
Member for
21 years 3 monthsRE: MSP2000 converion P3
hi,
anyone able to help me pleeeeease???
Member for
19 years 1 monthRE: MSP2000 converion P3
i suggest you upgrade now, (i like the copy & paste in P6), but IDs...(still trying to work out)!
Member for
21 years 3 monthsRE: MSP2000 converion P3
Hi,
thanks for the answers.
well the company works with P3 and not P6.
I looked on Paul Harris site - cant find the paper....
If you can send me the exact link and/or the msp applet I would appreciate it very much.
cheers
Sylvia
Member for
18 years 5 monthsRE: MSP2000 converion P3
Dear,
Theres a paper on Paul Harriss website for converting MSP2000 to P3.
U can find it on www.eh.com.au
Cheers,
Member for
19 years 1 monthRE: MSP2000 converion P3
try P6
Member for
21 years 3 monthsRE: MSP2000 converion P3
Hi,
Thanks, but it DOES NOT work - here why...
Bluewater Project Management Services, LLC no longer sells or supports the MPX Translator or Project Partner products
So the question still remain - how can I get out of this dilema?
cheers
Sylvia
Member for
18 years 5 monthsRE: MSP2000 converion P3
Hi Sylvia,
You have to download converter file from primavera knowledge base to do the conversion of MSP 2000 file format directly into MPX file, then Click --> Tools --> MPX conversion utility, then select the MPX file to convert it into P3 files
You hav the necessary stuff using this link
http://www.bluewaterpm.com/solutions/mpx.asp
Cheers,
Ravi