MSP doesnt know the clear distinction between WBS and activities as Primavera does; this also means the OBS mechanism isnt available out of the box.
What you can do in MSP is create the OBS in an Outline Code, but you need to guard the consistency between activities, summary tasks and your OBS code. (in other words, youll need to make sure that all activities underneath a WBS (i.e. summary task) have the same OBS code)
Member for
17 years 10 monthsRE: OBS & MSP
Hello Niek,
Thank you very much for your worthful information.
Best regards,
Hamed
Member for
20 years 7 monthsRE: OBS & MSP
Hello Hamed,
MSP doesnt know the clear distinction between WBS and activities as Primavera does; this also means the OBS mechanism isnt available out of the box.
What you can do in MSP is create the OBS in an Outline Code, but you need to guard the consistency between activities, summary tasks and your OBS code. (in other words, youll need to make sure that all activities underneath a WBS (i.e. summary task) have the same OBS code)
Hope this explains,
Niek.