the administrator can allow the resources to enter actual hours per day / actual days per week instead of % complete; I cannot explain the whole process as I do not have MS Project Server currently loaded on my traveling PC
this way, the resource would enter actual hours the day the task actually starts, and not the day the task should start
Member for
22 years 9 monthsRE: MS Project Server - New Forecast Dates
Scott,
the administrator can allow the resources to enter actual hours per day / actual days per week instead of % complete; I cannot explain the whole process as I do not have MS Project Server currently loaded on my traveling PC
this way, the resource would enter actual hours the day the task actually starts, and not the day the task should start
Does it help?
Alexandre