you can use start or finish varience columns to show this or if you are using 2003 or later there is a wizard to compare 2 project files and listt all the changes between them
yes i did but i want an empty cell telling me that this activity is delayed by 20 days or 10 and so on for each activity can i add an empty column and make formula to substract the start date of every activity and the status date???
Member for
19 years 3 monthsRE: how can i do this
you can use start or finish varience columns to show this or if you are using 2003 or later there is a wizard to compare 2 project files and listt all the changes between them
hope that helps
Dave
Member for
18 years 5 monthsRE: how can i do this
Hi Ahmed,
There must be a column of DURATION VARIANCE. Double Click on the column head and add this column in the field name.
This shud solve ur problem
Member for
18 years 9 monthsRE: how can i do this
yes i did but i want an empty cell telling me that this activity is delayed by 20 days or 10 and so on for each activity can i add an empty column and make formula to substract the start date of every activity and the status date???