go to Tools, OPtions, Calculation, use the options #2 to #5 under Calculation options for (current) project (dont know the exact name in English as I am using the French version)
looks like MS Project would like to simulate P3, with limited success
Alexandre
Member for
19 years 11 months
Member for20 years
Submitted by Andrew Owenson on Mon, 2007-07-09 09:32
Cannot help with the how, but if you go to Tools, Tracking, Update Project. Tick the reschedule uncompleted work, as long as your status date is correct the activities will adjust to the right of the status date - works for me
Member for
22 years 9 monthsRE: Status Date and Work Shown to be Perfromed Before
Hello,
go to Tools, OPtions, Calculation, use the options #2 to #5 under Calculation options for (current) project (dont know the exact name in English as I am using the French version)
looks like MS Project would like to simulate P3, with limited success
Alexandre
Member for
19 years 11 monthsRE: Status Date and Work Shown to be Perfromed Before
N
Cannot help with the how, but if you go to Tools, Tracking, Update Project. Tick the reschedule uncompleted work, as long as your status date is correct the activities will adjust to the right of the status date - works for me
Best Regards
Andrew