Optimum activity numbers in project for best schedule

Member for

20 years 7 months

What is the average size of your activities?



Don’t forget that you need to update the schedule and recalculate the critical path after the remaining work is rescheduled. This effort can exceed your weekly/monthly update capacity if the activities are very small.



H.T.H.