Microsoft Project Member for 20 years 7 months Member for 20 years 8 months Submitted by Niek Zonneveld on Fri, 2007-07-06 12:29 Permalink RE: Optimum activity numbers in project for best schedule What is the average size of your activities? Dont forget that you need to update the schedule and recalculate the critical path after the remaining work is rescheduled. This effort can exceed your weekly/monthly update capacity if the activities are very small. H.T.H. Log in or register to post comments
Member for 20 years 7 months Member for 20 years 8 months Submitted by Niek Zonneveld on Fri, 2007-07-06 12:29 Permalink RE: Optimum activity numbers in project for best schedule What is the average size of your activities? Dont forget that you need to update the schedule and recalculate the critical path after the remaining work is rescheduled. This effort can exceed your weekly/monthly update capacity if the activities are very small. H.T.H.
Member for
20 years 7 monthsRE: Optimum activity numbers in project for best schedule
What is the average size of your activities?
Dont forget that you need to update the schedule and recalculate the critical path after the remaining work is rescheduled. This effort can exceed your weekly/monthly update capacity if the activities are very small.
H.T.H.