Night shift

Member for

18 years 1 month

Thanx. that makes sense. just needed to say it outloud to see how the logic works.

Member for

24 years 6 months

Dale



If you want to do this for 5 days the calendar settings would be;



Sunday work is 8:00pm to midnight

Monday is Midnight to 6:00am

Tuesday to Thursday as Monday

Friday is Midnight to 6:00am



Look at the MSP Night Shift Calendar this will give you a lead.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

18 years 1 month

can i just expand on the question. i wish to start work at 20:00 (8pm) and finish 06:00 (6am). However MS Project will not allow me to do this, telling me that my end time must be after my start time, how can it set my working day to for example.



07:00 to 12:00

12:30 to 17:00

17:30 to 20:00

20:30 to 02:00

Member for

24 years 6 months

If you have a standard load of MSP then have a look at how MSP creates the Night shift calendar in “Project 1” when you open the software.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au