MS Project Server - Project Interim variance

Member for

18 years 5 months

In the customize field dialog there is a section called "Calculation for task and group summary rows". In it select "Use Formula". This will have the variance calculated at the summary task levels within your project, including at the project summary task level.



Remember to use an Enterprise level field if you want this to be calculated for all your projects.