In the customize field dialog there is a section called "Calculation for task and group summary rows". In it select "Use Formula". This will have the variance calculated at the summary task levels within your project, including at the project summary task level.
Remember to use an Enterprise level field if you want this to be calculated for all your projects.
Member for
18 years 5 monthsRE: MS Project Server - Project Interim variance
Great.
Yes it is one of those seetings that slips by many people.
Cheers
Member for
22 years 2 monthsRE: MS Project Server - Project Interim variance
Thanks Brian - that works!
I must remember to select the "use Formula" option in future.
Cheers
Steve
Member for
18 years 5 monthsRE: MS Project Server - Project Interim variance
In the customize field dialog there is a section called "Calculation for task and group summary rows". In it select "Use Formula". This will have the variance calculated at the summary task levels within your project, including at the project summary task level.
Remember to use an Enterprise level field if you want this to be calculated for all your projects.