Finish Milestone in MS Project

Member for

9 years 6 months

The Lag is safest.

Member for

19 years

Bo, good observation about MSP milestones as compared to others.

i suppose in MSP a milestone is an "indicator" (unlike other software which traet it as an activity). it just indicate the start or end of the predecessor depending on the logic type (SS will indicate the start)



as for milestone without a predecessor..

definitely it has to be a start milestone since there is nothing for it to indicate as an end of...



so i suppose Trevor provided the only solution to ur requirement... play around with the lag to get the date u prefer.

Member for

19 years 8 months

Well, just found the answer to part of the question: Enter the date in the "Finish"-column instead of the "Start"-column.



However, I still have a problem in certain situations where the milestone do have predecessors, e.g. say I have completion of "Snagging" and/or "Test/Commissioning" activities on day X and "Handover of Project" on day X+1. If "Handover" is just a milestone linked with FS and duration of 0, it will also end of day X instead of X+1, i.e. on site I’ll finish my activities late one evening and the Client/Owner won’t take over the following morning, but the programme will show me he’ll take over the same evening (which is not correct because he is home sleeping).



Do I "cheat" MS Project again and make that milestone (Handover) have a duration of 1 day?



Regards,



Bo