I ahd in mind that it was possible for MSP to display the progress line ahead of schedule; my mistake, I made the confusion with Sciforma Project Scheduler.
Look at the following page for a good example of how to use the progress lien:
As per the discussion on the following page, MS Project is RIGHT when not displaying the progress line ahead of schedule; there is the way of setting up the options if you want to display the p-line:
Member for
22 years 9 monthsRE: Progress Line
Jaco,
I ahd in mind that it was possible for MSP to display the progress line ahead of schedule; my mistake, I made the confusion with Sciforma Project Scheduler.
Look at the following page for a good example of how to use the progress lien:
http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=595
As per the discussion on the following page, MS Project is RIGHT when not displaying the progress line ahead of schedule; there is the way of setting up the options if you want to display the p-line:
http://www.mcse.ms/message2168898.html
I hope it helps
Alexandre