How reliable is peak unit values.?

Member for

22 years 9 months

Vinod,

as you entered 16 hours on the last day, MS Project put the all 16 hours at the same time where the initial 4 hours were, the morning.

click zoom in (the magnifier +) to see the time more in details

if you want to spread the 16 hours during the whole day, enter 8 hours during the morning and 8 hours in the afternoon; ms project will display a warning saying the resource is assigned beyond the task limit on the fixed duration tasks; click OK

the resource graph will show peak unit = 2.

Alexandre