Copying Activities and Keeping Ext Links

Member for

22 years 9 months

Mark,

I don’t think it’s faisable, as MS project stores the external link from the current project task to the root and to the external project task.

You could edit the external link in the Predecessor or Successor column, may be easier than create the link from scratch

Alexandre