So we can conclude that MSP can schedule in minutes, hours, days, weeks and more, but is not able to show a progress line thats on the exact Status Date set in the project (ie. Oct 14 16:00) ??
I find this very hard to believe. A planning package that has a minimum planning unit of minutes and cant even set the progress line on hours. Odd.
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Fri, 2006-10-13 04:44
Member for
22 years 9 monthsRE: Progress line question (Bug?)
Believe it or not...
There are plenty of things that you would like MSP to do and that MSP does not..
THIS is not a bug, you might rather call it a non-functionnality".
Send mails to your nearest MS representative to suggest this functionnality be implemented in the next version.
Alexandre
Member for
21 years 6 monthsRE: Progress line question (Bug?)
Nice answer.
So we can conclude that MSP can schedule in minutes, hours, days, weeks and more, but is not able to show a progress line thats on the exact Status Date set in the project (ie. Oct 14 16:00) ??
I find this very hard to believe. A planning package that has a minimum planning unit of minutes and cant even set the progress line on hours. Odd.
Member for
22 years 9 monthsRE: Progress line question (Bug?)
HI,
this the way MS Project works!
Alexandre