Changing Date ..Man Hours Change

Member for

20 years 11 months

Thank you very much Alexandre. Only one activity still showing the same attribute. Let’s see

Once more thanks a lot for your kind information.

Member for

22 years 9 months

Ali,

Double-clic the task to open "Task Information", display "Advanced", change "Task Type" to "Fixed Work" to have the assignement rate changed instead of the amount of work.

Select together all the tasks you want and click the Task Information icon, then continue as above

Open Tools, Options, Schedule and change Task Type to Fixed Work to setup the tasks before you create it.

All the best