hi Zhang ,



I think 16% is correct . My logic being a resource is available to us as per their base calanders , so it is with respect to that time available we should fill in the assignment units.



Any different Views ?

Member for

20 years 6 months

It’s a complex issue.



In MSP there are 3 types of task, fixed duration, fixed work and fixed units. they act differently when assign/change recource.



for your question, use 50%, but maybe the duration will change based on task type.



Goto online help for details for task type,then try it