Hi,



you can input these info. in ’Resource Usage View’

insert a column ’overtime work’



as for your example, put 11hrs in work, and 3hrs in overtime work



for your 2nd question, i’m afraid the first row can’t be deleted.

Member for

19 years 2 months

hi ,



once i entered resource cost in Resource information dialog box , can someone tell me as why cant i delete that information once i have clicked OK.