Project Calendars in MS Project

Member for

19 years 5 months

Hi Alexandre



Thanks for the comments and reply. At the end of the day that is all one can do, is be careful and try to achieve accuracy. I always want my plan to reflect reality as close as possible.



Kind regards from SA

Member for

22 years 9 months

Hello,

Basically, you cannot do anything:

Calendar options are used by MSP to compute how many hours per day / per week, how many days per month a resource available 100% is able to work; e.g. Alexandre is available 100%, he will work 8 hours per day on a 5 day task, that makes a 40 hour workload on this task.

MSP is not very good at managing a project with several task calendars; you should be very cautious when building and checking your schedule.

All the best

Alexandre