Microsoft Project Member for 19 years 8 months Member for 19 years 8 months Submitted by jatin mamman on Mon, 2006-07-24 01:10 Permalink RE: Projected End Date of Project in MSP thank you sir, am finally able to break the Da Vinci Code of my project Cheers jatin Member for 19 years 5 months Member for 19 years 5 months Submitted by James Griffiths on Sun, 2006-07-23 06:07 Permalink RE: Projected End Date of Project in MSP Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file. James :-) Member for 19 years 10 months Member for 19 years 10 months Submitted by Masood Ahmed Farooqi on Sun, 2006-07-23 02:38 Permalink RE: Projected End Date of Project in MSP now proceed as follows go to TOOL/TRACKING?UPDATE PROJECT/ select o RESCHEDULE UNCOMPLETED WORK TO START __*_____ * date of progress finally select O ENTIRE PROJECT goodluck MASOOD AHMED Member for 19 years 5 months Member for 19 years 5 months Submitted by James Griffiths on Sat, 2006-07-22 10:46 Permalink RE: Projected End Date of Project in MSP Jatin, After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change. James. Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Wed, 2006-07-05 06:13 Permalink RE: Projected End Date of Project in MSP you can find this information from menu: Project - porject information... - finish date or you can show the porject summary bar, it also give you the end date Member for 19 years 8 months Member for 19 years 8 months Submitted by jatin mamman on Thu, 2006-06-29 02:08 Permalink RE: Projected End Date of Project in MSP Precisely Sir, thats what i am searching for, i.e the Updated End Date of the Project. In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date. So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project. Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else? Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates. Awaiting your valuable comments Regards Jatin Member for 19 years 10 months Member for 19 years 10 months Submitted by Masood Ahmed Farooqi on Tue, 2006-06-27 12:12 Permalink RE: Projected End Date of Project in MSP after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf A- PLAIN SCHEDULING 1. dependin upon link/relationship 2. actual progress input faster /slower than baseline 3. any constraint date B - SCHEDULING WITH RESOURCE LOADING 1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any ) 2. also depending on link & res. availability , later time of among both regds M . FAROOQI Log in or register to post comments
Member for 19 years 8 months Member for 19 years 8 months Submitted by jatin mamman on Mon, 2006-07-24 01:10 Permalink RE: Projected End Date of Project in MSP thank you sir, am finally able to break the Da Vinci Code of my project Cheers jatin
Member for 19 years 5 months Member for 19 years 5 months Submitted by James Griffiths on Sun, 2006-07-23 06:07 Permalink RE: Projected End Date of Project in MSP Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file. James :-)
Member for 19 years 10 months Member for 19 years 10 months Submitted by Masood Ahmed Farooqi on Sun, 2006-07-23 02:38 Permalink RE: Projected End Date of Project in MSP now proceed as follows go to TOOL/TRACKING?UPDATE PROJECT/ select o RESCHEDULE UNCOMPLETED WORK TO START __*_____ * date of progress finally select O ENTIRE PROJECT goodluck MASOOD AHMED
Member for 19 years 5 months Member for 19 years 5 months Submitted by James Griffiths on Sat, 2006-07-22 10:46 Permalink RE: Projected End Date of Project in MSP Jatin, After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change. James.
Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Wed, 2006-07-05 06:13 Permalink RE: Projected End Date of Project in MSP you can find this information from menu: Project - porject information... - finish date or you can show the porject summary bar, it also give you the end date
Member for 19 years 8 months Member for 19 years 8 months Submitted by jatin mamman on Thu, 2006-06-29 02:08 Permalink RE: Projected End Date of Project in MSP Precisely Sir, thats what i am searching for, i.e the Updated End Date of the Project. In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date. So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project. Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else? Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates. Awaiting your valuable comments Regards Jatin
Member for 19 years 10 months Member for 19 years 10 months Submitted by Masood Ahmed Farooqi on Tue, 2006-06-27 12:12 Permalink RE: Projected End Date of Project in MSP after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf A- PLAIN SCHEDULING 1. dependin upon link/relationship 2. actual progress input faster /slower than baseline 3. any constraint date B - SCHEDULING WITH RESOURCE LOADING 1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any ) 2. also depending on link & res. availability , later time of among both regds M . FAROOQI
Member for
19 years 8 monthsRE: Projected End Date of Project in MSP
thank you sir,
am finally able to break the Da Vinci Code of my project
Cheers
jatin
Member for
19 years 5 monthsRE: Projected End Date of Project in MSP
Thankyou Masood. I was being lazy and hoped that he himself would discover how to do this. It should be in the HELP file.
James :-)
Member for
19 years 10 monthsRE: Projected End Date of Project in MSP
now proceed as follows
go to TOOL/TRACKING?UPDATE PROJECT/
select o RESCHEDULE UNCOMPLETED WORK TO START __*_____
* date of progress
finally select O ENTIRE PROJECT
goodluck
MASOOD AHMED
Member for
19 years 5 monthsRE: Projected End Date of Project in MSP
Jatin,
After inputting progress, always remember to "Reschedule Uncompleted Work". If you do not do this, then the project end-date will not change.
James.
Member for
20 years 6 monthsRE: Projected End Date of Project in MSP
you can find this information from menu:
Project - porject information... - finish date
or you can show the porject summary bar, it also give you the end date
Member for
19 years 8 monthsRE: Projected End Date of Project in MSP
Precisely Sir,
thats what i am searching for, i.e the Updated End Date of the Project.
In my case, Some Activities have crossed their Basline End Date, and the Actual End Date is greater than the Baseline End Date.
So i am interested in knowing, if this has caused any change to the Scheduled End Date of the project.
Would this be reflected in the Project Information (Statistics) part or would it be reflected some place else?
Because as of now, nothing is being refleted in Proj Info (Stats) barring the Baseline Dates.
Awaiting your valuable comments
Regards
Jatin
Member for
19 years 10 monthsRE: Projected End Date of Project in MSP
after saving baseline , & progress input , you might have a same end date as of base line or another updated end date depending upon teh followinf
A- PLAIN SCHEDULING
1. dependin upon link/relationship
2. actual progress input faster /slower than baseline
3. any constraint date
B - SCHEDULING WITH RESOURCE LOADING
1. in case of efforts driven tsak , availabblity of res. as per relevent res. calander ( if any )
2. also depending on link & res. availability , later time of among both
regds
M . FAROOQI