Time - Unit for Links

Member for

20 years 6 months

By defult Lag /duration is shown in day



Check ’tools’-->’Options’--> ’Schedule’ tab --> ’Duration is entered in’ you can select min/day/week...



When you type in Lag, you can use:



"2d" or " 2day" or "2days" ---- 2 days

"2ed" or "2eday" or "2edays" ---- 2 elapsed day

"2m" or "2min" or "2minute" ---- 2 minutes

you can try week month year...

Member for

20 years 3 months

Hello,



here some more information: I’m looking for the setting how to show the LAG in days.



Thanks Hannes

Member for

20 years 6 months

MSP always use minute as planning unit.

But it can show it as day/week/month based on you setting & input

Member for

20 years 6 months

Pls give more information ,



time-unit for successors for duration or lag?