Microsoft Project Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Tue, 2006-05-30 01:19 Permalink RE: Resources I think you need to update the resource assignment manually, the program do not know which resource should be increased for which task. In general, you may check all critical tasks to find out the tasks that their duration can be shortened to shorten the duration, you need to increase resource, try to start with the cheapest ( cost effective) Log in or register to post comments
Member for 20 years 6 months Member for 20 years 7 months Submitted by Zhang Haixiang on Tue, 2006-05-30 01:19 Permalink RE: Resources I think you need to update the resource assignment manually, the program do not know which resource should be increased for which task. In general, you may check all critical tasks to find out the tasks that their duration can be shortened to shorten the duration, you need to increase resource, try to start with the cheapest ( cost effective)
Member for
20 years 6 monthsRE: Resources
I think you need to update the resource assignment manually,
the program do not know which resource should be increased for which task.
In general, you may check all critical tasks to find out the tasks that their duration can be shortened
to shorten the duration, you need to increase resource, try to start with the cheapest ( cost effective)