Lag’s Calendar

Member for

24 years 6 months

There are two other options for lags:



Elapsed lags, say FS+10edays will give you an elapsed lag ignoring the Successor calendar.



Percent Lags, say FS-50% which will allow the successor to start 50% through the duration of the predecessor.



P3 and SuerTrak use the predecessor calendar but Primavera Enterprise gives several options.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

18 years 11 months

In MSP 2003, working days in lag relationships are computed based on the Successor Activity’s calender. This defaults to the Project Calendar if no other calendar is specified for the successor activity. (I think P3 uses the Predessesor’s calendar).



[This is a correction I just learned today, so I thought I’d post it for the record.]

BR, tom

Member for

19 years 5 months

It uses Default Calendar, Unless yuo had configured and assign a Task Calendar for the tasks reference to

Member for

20 years

Thanks Ronald.



I’m not a MSP user ... so i dont use to read MSP threads ... thats why i didn’t know about that.



Thanks again.



Regards.



Marcio Eduardo

Member for

22 years 10 months

I have been told that MS Project lags are calculated using the Default Calendar.

Member for

20 years

And where can I configure this??



Thanks