Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2006-03-05 08:30 Permalink RE: Re-scheduling in MSP 2000 Hello, this "nuance" does not exist in MSP 2K Go to Tools, Tracking, Update Project, and use "reschedule uncompleted work to start" (as from the status date) It does the same thing. Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2006-03-05 08:30 Permalink RE: Re-scheduling in MSP 2000 Hello, this "nuance" does not exist in MSP 2K Go to Tools, Tracking, Update Project, and use "reschedule uncompleted work to start" (as from the status date) It does the same thing. Alexandre
Member for
22 years 9 monthsRE: Re-scheduling in MSP 2000
Hello,
this "nuance" does not exist in MSP 2K
Go to Tools, Tracking, Update Project, and use "reschedule uncompleted work to start" (as from the status date)
It does the same thing.