Do your resources (or any) have a different calendar from the project’s one?.
Spli tasks and dotted / dashed line display a peiod withun the task duration where nobody is at work, possibly due to a non-working day in the resource calendar.
Also check the task info dialog, Advanced tab: does the task use a specific calendar?
Member for
22 years 9 monthsRE: Work Effort wrong calculations and bars split
Hello,
Do your resources (or any) have a different calendar from the project’s one?.
Spli tasks and dotted / dashed line display a peiod withun the task duration where nobody is at work, possibly due to a non-working day in the resource calendar.
Also check the task info dialog, Advanced tab: does the task use a specific calendar?
have a good Xmas
Alexandre