Microsoft Project Member for 20 years 8 months Member for 20 years 8 months Submitted by Sukumaran Suba… on Mon, 2005-10-03 05:30 Permalink RE: Project/Resource Query Dave, ???????? "Tasks are independent and not linked to each other. But when you update the start and finish dates for one task the dates for other tasks change automatically." Check your schedule again. Go to Format/Layout and check Links. If you marked the links invisible box, remove it and marked the links visible box. Now you are able the see the links. Check what are the predecessor and successor for each task and update it accordingly. HTH Log in or register to post comments
Member for 20 years 8 months Member for 20 years 8 months Submitted by Sukumaran Suba… on Mon, 2005-10-03 05:30 Permalink RE: Project/Resource Query Dave, ???????? "Tasks are independent and not linked to each other. But when you update the start and finish dates for one task the dates for other tasks change automatically." Check your schedule again. Go to Format/Layout and check Links. If you marked the links invisible box, remove it and marked the links visible box. Now you are able the see the links. Check what are the predecessor and successor for each task and update it accordingly. HTH
Member for
20 years 8 monthsRE: Project/Resource Query
Dave,
????????
"Tasks are independent and not linked to each other.
But when you update the start and finish dates for one task the dates for other tasks change automatically."
Check your schedule again. Go to Format/Layout and check Links. If you marked the links invisible box, remove it and marked the links visible box.
Now you are able the see the links. Check what are the predecessor and successor for each task and update it accordingly.
HTH