Microsoft Project Member for 22 years 11 months Member for 22 years 11 months Submitted by Tony McClennon on Wed, 2005-07-13 06:55 Permalink RE: Summary Task Duration Display Sukumaran - many thanks, just the thing.I must have been having one of those "forgetful" moments!!! Regards, Tony Member for 20 years 8 months Member for 20 years 8 months Submitted by Sukumaran Suba… on Wed, 2005-07-13 06:49 Permalink RE: Summary Task Duration Display Go to Tools > Options > Schedule and in the following field "DURATIONS IS ENTERED IN" change to either Weeks or Months. Regards. Member for 22 years 11 months Member for 22 years 11 months Submitted by Tony McClennon on Wed, 2005-07-13 06:28 Permalink RE: Summary Task Duration Display Sorry - should have mentioned that I am working with MSP2000. Tony Log in or register to post comments
Member for 22 years 11 months Member for 22 years 11 months Submitted by Tony McClennon on Wed, 2005-07-13 06:55 Permalink RE: Summary Task Duration Display Sukumaran - many thanks, just the thing.I must have been having one of those "forgetful" moments!!! Regards, Tony
Member for 20 years 8 months Member for 20 years 8 months Submitted by Sukumaran Suba… on Wed, 2005-07-13 06:49 Permalink RE: Summary Task Duration Display Go to Tools > Options > Schedule and in the following field "DURATIONS IS ENTERED IN" change to either Weeks or Months. Regards.
Member for 22 years 11 months Member for 22 years 11 months Submitted by Tony McClennon on Wed, 2005-07-13 06:28 Permalink RE: Summary Task Duration Display Sorry - should have mentioned that I am working with MSP2000. Tony
Member for
22 years 11 monthsRE: Summary Task Duration Display
Sukumaran - many thanks, just the thing.I must have been having one of those "forgetful" moments!!!
Regards,
Tony
Member for
20 years 8 monthsRE: Summary Task Duration Display
Go to Tools > Options > Schedule and in the following field "DURATIONS IS ENTERED IN" change to either Weeks or Months.
Regards.
Member for
22 years 11 monthsRE: Summary Task Duration Display
Sorry - should have mentioned that I am working with MSP2000.
Tony