Thanks. All in bar style, just finish a test on Project2k and work. I do a backward scheduling and store the late start/finish in a custome field. Then do the forwars scheduling scheduling again to back to early dates. Now display both early and late bars by Bar style.
I think what MKTSE means, is make sure your task has a 3 day float and only 1 day duration. In the Bar Style Options, put Float bar over the other bars defined in the Bar Style Options i.e. put the float bar as the last row in your bar definition.
China - thanks very much for your reply but I am not sure how do do what you suggest. Can you describe what I do from Gantt Chart view as I have tried all the buttons on the task information box with no success.
Member for
23 years 8 monthsRE: Fixed task duration
Thanks. All in bar style, just finish a test on Project2k and work. I do a backward scheduling and store the late start/finish in a custome field. Then do the forwars scheduling scheduling again to back to early dates. Now display both early and late bars by Bar style.
Member for
16 years 9 monthsRE: Fixed task duration
I think what MKTSE means, is make sure your task has a 3 day float and only 1 day duration. In the Bar Style Options, put Float bar over the other bars defined in the Bar Style Options i.e. put the float bar as the last row in your bar definition.
SE
Member for
16 years 9 monthsRE: Fixed task duration
China - thanks very much for your reply but I am not sure how do do what you suggest. Can you describe what I do from Gantt Chart view as I have tried all the buttons on the task information box with no success.
Thanks again
Chris
Member for
23 years 8 monthsRE: Fixed task duration
Use the calcaulated float the work out the start/finish dates of float bar and put the bar against the normal earier bar.