Ive had a play around with it and as a workaround have added it as a material cost and loaded the number of units in the resource allocation to equal the number of days that task requires.
If anyone can think of a smarter way of doing it, please let me know.
Dan
Member for
22 years 6 months
Member for22 years7 months
Submitted by Will Russell on Tue, 2004-02-24 12:58
Member for
16 years 9 monthsRE: Resource Expenses
Thanks
Ive had a play around with it and as a workaround have added it as a material cost and loaded the number of units in the resource allocation to equal the number of days that task requires.
If anyone can think of a smarter way of doing it, please let me know.
Dan
Member for
22 years 6 monthsRE: Resource Expenses
Using the Cost tab in the Resource Information box you can put in specific costs for certain periods of time as you wanted.
Will