From the timescale form you should, when using 2002 or 2003 select to show two teirs.
Then format on Tier to show the Unit of Years with the Label showing the Year date format you require.
Move to the other Tier select the time Unit of Weeks and scroll down to the bottom of the Label list and select the required Week Numbering format you require. There are lots of options for formatting weeks from the start or end date.
Unlike P3 you are not able to nominate a date to start the week numbering from.
Member for
22 years 11 monthsRE: Time scale display problems
Paul, I fixed the link you posted in your signature. The PP forum needs double quotes in the href tag.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Member for
24 years 6 monthsRE: Time scale display problems
From the timescale form you should, when using 2002 or 2003 select to show two teirs.
Then format on Tier to show the Unit of Years with the Label showing the Year date format you require.
Move to the other Tier select the time Unit of Weeks and scroll down to the bottom of the Label list and select the required Week Numbering format you require. There are lots of options for formatting weeks from the start or end date.
Unlike P3 you are not able to nominate a date to start the week numbering from.
Regards
Paul E Harris
www.eh.com.au