Microsoft Project Member for 21 years 10 months Member for 21 years 10 months Submitted by Dinesh Kumar on Mon, 2004-02-16 05:47 Permalink RE: Current Date column in MSP2000 Hi, Choose insert column>Start 1/Text 1>OK Right click on column top and choose customize fields and choose functions then choose Date() or Now()to get system date and set formula according to your requirement to get desired date. Thanks & regards Dinesh Log in or register to post comments
Member for 21 years 10 months Member for 21 years 10 months Submitted by Dinesh Kumar on Mon, 2004-02-16 05:47 Permalink RE: Current Date column in MSP2000 Hi, Choose insert column>Start 1/Text 1>OK Right click on column top and choose customize fields and choose functions then choose Date() or Now()to get system date and set formula according to your requirement to get desired date. Thanks & regards Dinesh
Member for
21 years 10 monthsRE: Current Date column in MSP2000
Hi,
Choose insert column>Start 1/Text 1>OK
Right click on column top and choose customize fields and choose functions then choose Date() or Now()to get system date and set formula according to your requirement to get desired date.
Thanks & regards
Dinesh