Task duration depends on other task

Member for

23 years 8 months

Beste M, Dear M,



Altough were dutch, i will answer this in english. Best way to solve this problem is probably to set up a structure in which codes identify the related activities. In this way you can, after modifications to the schedule, run a macro to adjust related durations.



Its not a common solution but were both seeking new and creative alternatives, I guess!



Groeten,



Ed van der Tak

Aram Planning Consultants

The Netherlands

Member for

16 years 9 months

I am faily certain that the function you are looking for is not an inbuilt function of Microsoft Project 2000.



You could probably achieve something with a couple of milestones driven by successors with %lags and span them with a parent activity, but it would not be very elagant.



Regards



Paul E Harris

Eastwood Harris Pty Ltd