why so difficult... in prod rate there is slow, average and fast. U can categories manpower base on trends of each country.
Base on my experience, before we do each project, feasibility study report should be done...that the way we come out the prod rate norm. What i can say here that prod rate is use to get the nearest budget to be applied in costing / scheduling.
Member for
22 years 4 months
Member for22 years4 months
Submitted by Shahzad Munawar on Sat, 2006-05-20 11:01
Your suggestion is good but this cannot be implemented on this forum as the production rates vary from country to country and it seems difficult to update this variation in rates country wise in this forum on /weekly/monthly/yearly basis.
Moreover one suggestion is that each Company has its own database of production rates and update it on monthly or yearly basis so you may look into it.
Member for
19 years 6 months
Member for19 years7 months
Submitted by Richard Quek on Sat, 2006-05-20 05:54
Not sure whetehr planning planet know about the problem & in the process of resolving it?
Just a matter of interest since we have members from various country and continent, do any one wish to start a new tread on the subject of the variations in production rates between countries or continent? I am very much a notie to planning and would like to know more.
Thanks
Member for
19 years 7 months
Member for19 years7 months
Submitted by Riyah Suharto on Sat, 2006-05-20 05:10
i had taken a copy of all Production rates from planningplanet. if any1 needs the same, mail me ur emailid. shall mail u the same. till then allow webmasters 2 fix the bug.
Are we the only 4 people who cannot access production rates or does nobody else use them. Ive still had no reply from the PP webmaster so Im not even sure if the rates are avaliable.
CAN ANYONE HELP US!!!
Member for
19 years 6 months
Member for19 years7 months
Submitted by Richard Quek on Thu, 2006-04-13 19:05
Member for
16 years 9 monthsRE: problems with the Production Rates
Hi there,
Appologies. We thought this issue had been fixed. I will chase the tech team today to see where we are, and why it has not been resolved.
I will report back shortly.
Thanks PP Admin
Member for
19 years 6 monthsRE: problems with the Production Rates
Hey guys...
me too..
first of all, i thought that my computer problem...
then i fed-up for a while.
Finally i make up my mind to raise question in the forum.Lucky i found this forum...
Yes! I aggree it is very intresting corner to learn.
;-)
Member for
19 years 6 monthsRE: problems with the Production Rates
Hi,
Thank for the contributions & I believe this is a healthy situation for PP.
Let me start a new tread so as not to contaminate this tread.
See you all there.
Thanks
Member for
20 years 5 monthsRE: problems with the Production Rates
why so difficult... in prod rate there is slow, average and fast. U can categories manpower base on trends of each country.
Base on my experience, before we do each project, feasibility study report should be done...that the way we come out the prod rate norm. What i can say here that prod rate is use to get the nearest budget to be applied in costing / scheduling.
Member for
22 years 4 monthsRE: problems with the Production Rates
Richard
Your suggestion is good but this cannot be implemented on this forum as the production rates vary from country to country and it seems difficult to update this variation in rates country wise in this forum on /weekly/monthly/yearly basis.
Moreover one suggestion is that each Company has its own database of production rates and update it on monthly or yearly basis so you may look into it.
Member for
19 years 6 monthsRE: problems with the Production Rates
Hi Deva,
Thanks for the info.
Not sure whetehr planning planet know about the problem & in the process of resolving it?
Just a matter of interest since we have members from various country and continent, do any one wish to start a new tread on the subject of the variations in production rates between countries or continent? I am very much a notie to planning and would like to know more.
Thanks
Member for
19 years 7 monthsRE: problems with the Production Rates
Deva,
I would be appreciate if you could send me your prod rate record/file to my email .. riyah.suharto@inbox.com
Thanks in advance
|R|S|
Member for
20 yearsRE: problems with the Production Rates
Dear Stewart,
fwd ur mail id 4 me 2 fwd the production rates.
Member for
19 years 5 monthsRE: problems with the Production Rates
Dear, Devamalya De
I cant access too, please sent your copy me.
=> pattama_poo@hotmail.com
many thanks
regards,
PS. I not sure about pm, because Im new user in here.
Member for
20 yearsRE: problems with the Production Rates
dear all,
i had taken a copy of all Production rates from planningplanet. if any1 needs the same, mail me ur emailid. shall mail u the same. till then allow webmasters 2 fix the bug.
Member for
19 years 5 monthsRE: problems with the Production Rates
i have the same problem too. i get the following error message.
Microsoft OLE DB Provider for ODBC Drivers error 80040e31
[MySQL][ODBC 3.51 Driver][mysqld-5.0.18-nt]Out of range value adjusted for column CSO at row 1
/output_results.asp, line 177
Has anyone managed to fix this?
Member for
21 years 6 monthsRE: problems with the Production Rates
hi all,
same case with me, i had tried many times but to no avail, still a failure...
hope somebody will fix the system...it is really an interesting portion of this website...
Member for
19 years 7 monthsRE: problems with the Production Rates
Are we the only 4 people who cannot access production rates or does nobody else use them. Ive still had no reply from the PP webmaster so Im not even sure if the rates are avaliable.
CAN ANYONE HELP US!!!
Member for
19 years 6 monthsRE: problems with the Production Rates
Hi
I just join too but cant get production rate too. Can someone advise what I am doing wrong?
Thanks
Member for
19 years 7 monthsRE: problems with the Production Rates
Im having the same problem. I cant view any of the production rates etc. I have e-mailed PP but have not had a response.
Member for
19 years 7 monthsRE: problems with the Production Rates
Me either !
How to production rate for each categories ?