Productivity Tracking in P6

Member for

14 years 9 months

Hii Guys

I need Productivity Template and Progress Managment Template or format to make one for my ongoing project.

If possible please forward it to my e-mail my e-mail adress : syd.aijaz@gmail.com

Thanks

Aijaz Syed

Member for

24 years

Hi Mohammad,

In order to track productivity you need the following:

Plan Units per time - Budgeted Labour Units (Manhours or Mandays)

Earned Value - based on physical progress % complete (Budget Labour Units * % complete)

Actual Units per time - based on actual resources (manhours or mandays) this you need to input manually

Now, Productivity = Output (Earned) / Actual

Budgeted Labour Units - Progress Earned  = Remaining Units per time

Budgeted at Completion (BAC) or Forecast at Completion = Remaining Units per time / Productivity

Cheers mate,

Daniel