Middle East Planning and Controlling Member for 14 years 9 months Member for 14 years 9 months Submitted by notty on Sat, 2012-02-25 08:49 Permalink Hii GuysI need Productivity Hii Guys I need Productivity Template and Progress Managment Template or format to make one for my ongoing project. If possible please forward it to my e-mail my e-mail adress : syd.aijaz@gmail.com Thanks Aijaz Syed Member for 24 years Member for 24 years 1 month Submitted by Daniel Limson on Wed, 2012-02-22 11:27 Permalink Hi Mohammad,In order to track Hi Mohammad, In order to track productivity you need the following: Plan Units per time - Budgeted Labour Units (Manhours or Mandays) Earned Value - based on physical progress % complete (Budget Labour Units * % complete) Actual Units per time - based on actual resources (manhours or mandays) this you need to input manually Now, Productivity = Output (Earned) / Actual Budgeted Labour Units - Progress Earned = Remaining Units per time Budgeted at Completion (BAC) or Forecast at Completion = Remaining Units per time / Productivity Cheers mate, Daniel Log in or register to post comments
Member for 14 years 9 months Member for 14 years 9 months Submitted by notty on Sat, 2012-02-25 08:49 Permalink Hii GuysI need Productivity Hii Guys I need Productivity Template and Progress Managment Template or format to make one for my ongoing project. If possible please forward it to my e-mail my e-mail adress : syd.aijaz@gmail.com Thanks Aijaz Syed
Member for 24 years Member for 24 years 1 month Submitted by Daniel Limson on Wed, 2012-02-22 11:27 Permalink Hi Mohammad,In order to track Hi Mohammad, In order to track productivity you need the following: Plan Units per time - Budgeted Labour Units (Manhours or Mandays) Earned Value - based on physical progress % complete (Budget Labour Units * % complete) Actual Units per time - based on actual resources (manhours or mandays) this you need to input manually Now, Productivity = Output (Earned) / Actual Budgeted Labour Units - Progress Earned = Remaining Units per time Budgeted at Completion (BAC) or Forecast at Completion = Remaining Units per time / Productivity Cheers mate, Daniel
Member for
14 years 9 monthsHii GuysI need Productivity
Hii Guys
I need Productivity Template and Progress Managment Template or format to make one for my ongoing project.
If possible please forward it to my e-mail my e-mail adress : syd.aijaz@gmail.com
Thanks
Aijaz Syed
Member for
24 yearsHi Mohammad,In order to track
Hi Mohammad,
In order to track productivity you need the following:
Plan Units per time - Budgeted Labour Units (Manhours or Mandays)
Earned Value - based on physical progress % complete (Budget Labour Units * % complete)
Actual Units per time - based on actual resources (manhours or mandays) this you need to input manually
Now, Productivity = Output (Earned) / Actual
Budgeted Labour Units - Progress Earned = Remaining Units per time
Budgeted at Completion (BAC) or Forecast at Completion = Remaining Units per time / Productivity
Cheers mate,
Daniel