Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2023-01-31 10:15 Permalink Hi MohamedIf you are talking Hi Mohamed If you are talking about overlapping delays the usual rule is that you will be awarded an EOT but no prolongation costs. But the contract that you signed may not allow this. Best regards Mike T. Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2023-01-31 10:15 Permalink Hi MohamedIf you are talking Hi Mohamed If you are talking about overlapping delays the usual rule is that you will be awarded an EOT but no prolongation costs. But the contract that you signed may not allow this. Best regards Mike T.
Member for
19 years 10 monthsHi MohamedIf you are talking
Hi Mohamed
If you are talking about overlapping delays the usual rule is that you will be awarded an EOT but no prolongation costs.
But the contract that you signed may not allow this.
Best regards Mike T.