Days Due vs Days needed - what if you when you add up delays each month it is way more than needed?

Member for

12 years 5 months

Another way to phrase this: you are delayed 60 calendar days, the work gets done and it turns out it only delayed the job 50 days?  Do you get a 60 or 50 day extension and why?