Concurrent Delay: muti shipment materials, what if the start was delayed and fin. delayed but not in the middle?

Member for

24 years 9 months

Under all of the delay analysis protocols each delay event needs to be analysed separately.  If the event caused a delay to completion an EOT is warranted.  In the scenario described, any later claim has to allow for any previously approved (or claimed) EOT.

This situation is a good example of a scenario where ‘time windows’ are a useful approach.  The actual situation at the start of each time window is the baseline, and delay at the end of the window attributable to a claimable event is the EOT claim.

For more on this see: https://mosaicprojects.com.au/PMKI-ITC-020.php