2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost?

Member for

18 years

John, without knowing your contract pricing conditions and other circumstances, it's typical that daywork rates is used for additional work and that rates includes overhead, if that so, then 2-weeks extension will be fine...