Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2017-07-07 17:54 Permalink Hi AlanYes they Hi Alan Yes they should. Instruct your contractor to impact his dely events on the tasks leading to the milestones and refuse to consider anything else until it is done. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Fri, 2017-07-07 17:54 Permalink Hi AlanYes they Hi Alan Yes they should. Instruct your contractor to impact his dely events on the tasks leading to the milestones and refuse to consider anything else until it is done. Best regards Mike Testro
Member for
19 years 10 monthsHi AlanYes they
Hi Alan
Yes they should.
Instruct your contractor to impact his dely events on the tasks leading to the milestones and refuse to consider anything else until it is done.
Best regards
Mike Testro