Claim on Decrease in Scope and non validity on Completion Date

Member for

19 years 10 months

Hi Jithin

There may be many more delay events that are involved - only you will know if there are any.

Gary and I have given you two possible examples to look for - you have to find them.

Best regards

Mike Testro

Member for

14 years 7 months

Ok Mike and Gary,

 

So Only if the scope is increased or as You have said if the instruction to reduce was given late and then their is a change in design which will delay the construction then this case is applicable for EOT.

 

Regards

Jithin

Member for

19 years 10 months

Hi Jithin

One thing is certain and that is the completion date cannot be reducedd.

There may be scope for an EoT if the instruction to switch from 4 to 3 pipelines was issued late.

You may have scope for a rate increase if the cost of fixed price equipment is not covered on 3 pipelines when it was deployed for 4. This would be applicable for both onshore and offshore pipes.

Best regards

Mike Testro

Member for

16 years 7 months

 

Possibly if the change from 4 weels to 3 required some redesign of the pipework which delayed construction there might be a case for EOT.

 

But other than that, I can't see a valid claim.