EOT preparation methodology?

Member for

8 years 10 months

Thanks Mike for the advise.

rgds

Ajay

Member for

19 years 10 months

Hi Ajay

How complete are your as built records?

How responsive is the baseline programme?

What are your contract terms?

These are just a few of the things that need to be considered when selecting a dely analysis method.

The one method that works when there is no critical path and only rudimentary as built data is the Projected As Built method.

A demonstration is available for download from my website - www.expertdelayanalysis.com - for £35.00.

Best regards

Mike Testro