Thanks for responding. I already have suggested this to the planning manager, he after discussing with the commercial manager (who is looking after all the EOTs) that they are going to use the same programme and we will not get that rejected by the Employer (who is a government authority).
The second thing he said that if this programme will not give us the required we will use the same old (R01) for analysis but will not change the programme until it is rejected. I don’t understand that.
Member for
19 years 10 monthsHi TanveerNeither do I. If
Hi Tanveer
Neither do I. If you are in a hole do not keep digging.
Best regards
Mike T.
Member for
19 years 10 monthsHi TanveerNeither do I. If
Hi Tanveer
Neither do I. If you are in a hole do not keep digging.
Best regards
Mike T.
Member for
19 years 10 monthsHi Mr. TestroThanks for
Hi Mr. Testro
Thanks for responding. I already have suggested this to the planning manager, he after discussing with the commercial manager (who is looking after all the EOTs) that they are going to use the same programme and we will not get that rejected by the Employer (who is a government authority).
The second thing he said that if this programme will not give us the required we will use the same old (R01) for analysis but will not change the programme until it is rejected. I don’t understand that.
Cheers
Member for
19 years 10 monthsHi TanveerAbandon the
Hi Tanveer
Abandon the revisions.
Start again and get it right from the beginning.
Best regards
Mike T.