Thank you Mike. Same as my though and you have given a good clarity on my knowledge.
Now got the Point. The EOT would be only for 10 days as the client has delayed & the contractor has delayed + 20 days for which he has to pay the cost.
One more question,
If the Client has delayed the Project. Contract duration was 100 days and because of clients delay it became 110 days to complete the Project. Wouldnt the Contractor be eligible to ask LD Cost for 10 days ?
Member for
14 years 7 monthsThank you Mike. Same as my
Thank you Mike. Same as my though and you have given a good clarity on my knowledge.
Now got the Point. The EOT would be only for 10 days as the client has delayed & the contractor has delayed + 20 days for which he has to pay the cost.
One more question,
If the Client has delayed the Project. Contract duration was 100 days and because of clients delay it became 110 days to complete the Project. Wouldnt the Contractor be eligible to ask LD Cost for 10 days ?
Thanks
Jithin
Member for
17 years 4 monthsHi Mike,I was answering to
Hi Mike,
I was answering to Jithin's second question, where the delay is only by the Client for 10 days. No delay from the contractor.
Best Regards
Kannan
Member for
19 years 10 monthsHi KannanThe contractor
Hi Kannan
The contractor cannot claim costs for concurrent delays.
Best regards
Mike Testro
Member for
17 years 4 monthsHi Jithin, If the delay is
Hi Jithin,
If the delay is excusable (by client), the contractor can ask for the EOT as well as the cost of those 10 days.
Best Regards
Kannan
Member for
19 years 10 monthsHi JithinThe usual rules of
Hi Jithin
The usual rules of concurrent delays are:
10 days EoT to the contractor - no costs
20 days LAD's paid by the contractor.
Best regards
Mike Testro