You are facing the eternal problem that occurs with every delay analysis.
The original Baseline Programme is not fit for purpose and the task of re structuring it on a FS link basis is too difficult and again open to challenge that the exersise has been rigged to suit the outcome.
There are at least two ways forward:
1. If the as built records are complete then you can try a Collapsed As Built analysis which does not need a detailed baseline programme.
or
2. If the delay events impact on the start of key elements of the work - approval of design - power connection - employers free issue material etc then it is possible to adopt the Super Summary Method.
Member for
19 years 10 monthsHi SatishYou are facing the
Hi Satish
You are facing the eternal problem that occurs with every delay analysis.
The original Baseline Programme is not fit for purpose and the task of re structuring it on a FS link basis is too difficult and again open to challenge that the exersise has been rigged to suit the outcome.
There are at least two ways forward:
1. If the as built records are complete then you can try a Collapsed As Built analysis which does not need a detailed baseline programme.
or
2. If the delay events impact on the start of key elements of the work - approval of design - power connection - employers free issue material etc then it is possible to adopt the Super Summary Method.
Best regards
Mike Testro