EOT for a Particular Section of the Road

Member for

14 years 4 months

Thanks Mike for responding to my query and to your valuable comments.

Member for

19 years 10 months

Hi Prageeth

It depends what it says in your contract but a whole project cannot be split into sections for the sake of extensions of time.

What you have here is a concurrent delay situation where the contractor's late work is concurrent with excusable delays.

It may end up that you get your EoT for the Tie-ins but no delay related costs.

It may be that the Engineer is trying to achieve this result but in a roundabout way.

You will need to establish the direct cause and effect of each head of delay on the completion date and then set out your concurrency case.

Best regards

Mike Testro