Hi Anthony

Delay and disruption each need a different approach to establish entitlement to money.

To establish extension of time for delay you have to show cause and effect for each delay event individually.

Events that cause disruption need not be the same as those that caused delay but they still have to show direct cause and effect of each event on the value of the disrupted work.

You may have a bucket of data showing the total down time but it has to be allocated to each event that caused the disruption - otherwise you are presenting a global claim which will fail in the UK.

Best regards

Mike Testro