Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2011-04-11 10:12 Permalink Hi Raphael Rain days should Hi Raphael Rain days should be logged on the work calendar used for external works. This will generate extra time on all affected activities. Other delays should be impacted as usual. One possible scenario is that a delay event may push tasks into a bad weather zone. Another point is that inclement weather is usually classed as neutral causation and will releive LAD's but not attract costs. The concurrency factor can become quite complex in such situations. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2011-04-11 10:12 Permalink Hi Raphael Rain days should Hi Raphael Rain days should be logged on the work calendar used for external works. This will generate extra time on all affected activities. Other delays should be impacted as usual. One possible scenario is that a delay event may push tasks into a bad weather zone. Another point is that inclement weather is usually classed as neutral causation and will releive LAD's but not attract costs. The concurrency factor can become quite complex in such situations. Best regards Mike Testro
Member for
19 years 10 monthsHi Raphael Rain days should
Hi Raphael
Rain days should be logged on the work calendar used for external works. This will generate extra time on all affected activities.
Other delays should be impacted as usual.
One possible scenario is that a delay event may push tasks into a bad weather zone.
Another point is that inclement weather is usually classed as neutral causation and will releive LAD's but not attract costs.
The concurrency factor can become quite complex in such situations.
Best regards
Mike Testro