Rain Delay and Concurrency Issues

Member for

19 years 10 months

Hi Raphael

Rain days should be logged on the work calendar used for external works. This will generate extra time on all affected activities.

Other delays should be impacted as usual.

One possible scenario is that a delay event may push tasks into a bad weather zone.

Another point is that inclement weather is usually classed as neutral causation and will releive LAD's but not attract costs.

The concurrency factor can become quite complex in such situations.

Best regards

Mike Testro