Specification b/w Main & Sub Contractor

Member for

17 years 3 months

Dear Shahul,



There is a clause in FIDIC that calls for the financial records of payment made to subcontractor to works that were paid for by the client to be submitted upon asking for it.



With kind regards,



Samer

Member for

17 years 3 months

Dear Shahul,



It depends on the Conditions of the Subcontract agreement. You will need to follow the agreement between the Contractor and the Subcontractor.



With kind regards,



Samer