EOT Claim Analysis after 3 years of Project Completion

Member for

14 years 11 months

If the Contractor has not provided a reasonable analysis with adequate documentation and support to allow the engineer to make a determination, then the engineer can request additional information be provided. 

You can evaluate the EOT request by performing an independent analysis using the project records available.  I do this for a living and you can piece it together even if you do not have an as-built or project schedules (though they are helpful).  You can use daily reports, monthly reports, etc,.  It is time consuming and a bit like detective work but you must respond.  Based on the fact that it has been left idle, suggests the parties were not prepared to deal with it at the time, and now, years later it has to be dealt with.

If you need any asisstance evaluating the EOT or performing an independent analysis of delays and impacts I can help.  My email address is sfd@sfdelaneyconsulting.com.  If you would like to see my qualifications and experience, you can visit my website at sfdelaneyconsulting.com.

 

Best of luck,

Stephen F. Delaney

Member for

15 years 10 months

Hi  Vamsi,

You can recommend EOT retrospectively till accounts are finalized and so award of EOT issue can be resolved.If compensable delay has been experienced by the contractor,you have to take action as per contemporenous record which was to be submitted at appropriate time by the contractor as it is his resposibility to provide proof of actual costs incurred. In case he has failed to do so,he has to agree with Engineer's assessment.I hope this gives you some line of action.

Regards-Liaqat Hayat

Member for

17 years 3 months

Dear vamsi,



What was the Contractor doing during the past 3 years? How come he did not pursue the EOT?



How important is this issue? It is just paperwork, or does it have some impact on the remaining works?



With kind regards,



Samer

Member for

19 years 10 months

Hi Vamsi



Depending on the form of contract there is usually a period of time when the Engineer has to respond to an EoT claim and fix a reasonable extension.



If the Engineer did not do this then he is in breach of his duties and the Employer is right to be angry.



The Engineer must now review the claim as submitted and without delay issue his opinion as the EoT entitlement so that the final account can be settled.



This may lead to a dispute and the Engineers position will be weakened by his inactivity.



This may be balanced if the Contractor made no complaint at the time.



The Employer may try to recover any excess payment to the contractor which could have been avoided but for the Engineers tardiness.



Best regards



Mike Testro